1、Sahand Karimi CEO OptiGridTaryn LaneGM Hepburn EnergyCase Study:Deploying BESS at Hepburn Wind FarmBattery Asset Management Summit|August 2025 Battery Asset Management Summit|August 2025 OUR CO-OPERATIVE BACKSTORYOUR COMMUNITY IMPACT-Working on concept of co-located Battery since 2021-SMA inverter i

2、nstalled in 2021 for bushfire prevention is key asset to enable an affordable battery-Planning permit secured for 5MW solar and 10MWh battery in 2022-2023 Co-op successful under Federal Government program Community Batteries for Household Solar for a grant of$500,000-Project stage 1 will not trigger

3、 permit and will instead take Vic Gov exemption-Adding a battery system to soak up wind energy during low prices and sell stored energy at higher times,and creating a new value stream(FCAS revenue).-Increased volatility in energy market can be partially offset by battery on site-Negative pricing has

4、 jumped from 1-3%in 2022-23 to 12%in 2023-24-Simultaneously pursuing LTE for wind farm to go to 30-35 yearsContext:Project BackgroundEcosystem of Delivery Partners-OBrien Electrical Engineering,Procurement and Construction(EPC),SCADA upgrade-Sunwoda BESS-DNV grid connection-OptiGrid Energy Managemen

5、t System-Acacia Energy NEM settlement-SMA DC-DC converters-Flow Power retailing-Kinelli Solar and Seed Advisory DD support-BAL Legal-Fulcrum 3D Wind forecastContext:Bessie Project Overview-Installed on site at the wind farm,connected to existing inverter,existing grid connection-Capacity 2MW/5MWh-CA

6、PEX:$1.8m-$500k Federal Government grant-$120k CORENA zero interest community loan-$1.1m from 94 co-operative member debentures subscriptionsBusiness model results as per 2024Conservative approach to limit future surprises-15 years to align with reasonable extended life of wind farm(economic life is

word格式文档无特别注明外均可编辑修改,预览文件经过压缩,下载原文更清晰!
三个皮匠报告文库所有资源均是客户上传分享,仅供网友学习交流,未经上传用户书面授权,请勿作商用。
1. **项目背景**:Hepburn Wind Farm于2021年启动电池储能概念,2022年获规划许可,2023年获联邦政府50万美元资助,2024年部署2MW/5MWh电池(CAPEX 180万美元,含社区贷款)。 2. **核心挑战**:混合风电-电池系统需解决可再生能源预测误差、功率控制能力及输出波动性对收益的影响(如2分钟内功率骤降30%)。 3. **解决方案**:OptiGrid平台通过物理信息机器学习算法优化价格预测,整合SCADA数据,协同优化能源与FCAS市场交易,最大化收益。 4. **成果**:2024-2025年测试显示,混合系统较单一风电显著提升收益,通过精准建模捕捉极端价格事件,满足AEMO合规要求。 5. **关键数据**:负电价占比从2022-23年1-3%升至2023-24年约12%,电池可平抑价格波动并创造新价值流。
**混合能源如何盈利?** **电池如何优化风电?** **负电价如何应对?**
客服
商务合作
小程序
服务号
折叠