1、THE STATUS OF THE AQUAMARINEPROJECT OF HGSBudapest Hydrogen Summit15th April 2025Supporter:Background of the ProjectThe Status of the Aquamarine Project of HGS I kos Kriston CEO2Idea(2018-2019):to broaden storage services withhydrogen based energy storageFirst step:Project Aquamarine-State support i

2、n 2020Goals:To test surface process system on hydrogen toleranceby installing a H2production unit with all necessaryauxiliaries andBy carrying out supportive research programmesTimeframe:Start:1st February 2021.Duration:3 years(extension up to 4 years)Budget:Initial HUF 3 bn(EUR 7.9 million)State su

3、pport:cca.65%Research partners:4 universities and a R&D CenterOriginal plans1 Feb 2021 31 Jan 2023Electrolizer(2,5 MW)Wind turbinesPVsPower gridAs fuel in the compressorsInjection into the transmission systemPower plantsEnergy usage2023-2025Injection into the reservoirH2O2Supporter:Current Status Ap

4、ril 2025The Status of the Aquamarine Project of HGS I kos Kriston CEO31 Feb 2021 31 Jan 2025Electrolizer(2,5 MW)Wind turbinesPVsPower gridAs fuel in the compressorsInjection into the transmission systemPower plantsEnergy usage2026-2027H2O2Injection into the reservoirResearch and development program

5、completedConstruction CompletedCommissioning and test period:3 August,2023 23 February,202572-hours test run completed:19-23 February,2025Operating license available since 12 March,2025Expected date of commercial operation(max.400 m3/h production):May 2025,Contract negotiations for joining MVM Partn

6、ersBalancing Center is being finalized,Extras:-Tanker truck filling facility,-Contract with Messer as retailer of H2-Additional engineering services ready for saleSupporter:Playing an important role in flexibility services The Status of the Aquamarine Project of HGS I kos Kriston

word格式文档无特别注明外均可编辑修改,预览文件经过压缩,下载原文更清晰!
三个皮匠报告文库所有资源均是客户上传分享,仅供网友学习交流,未经上传用户书面授权,请勿作商用。
概括: 本文主要介绍了HGS布达佩斯氢能峰会上的Aquamarine项目状况。该项目始于2018-2019年,旨在利用氢能拓展储能服务,并得到了国家约65%的资金支持。项目时间跨度为2021年2月至2025年,预算约790万欧元。 关键点: 1. 项目目标:测试氢能容忍度,并开展相关研究。 2. 进展:2023年8月至2025年2月完成调试和测试运行,2025年5月预计商业运营。 3. 成果:已具备操作许可,产能达400m³/h。 4. 角色:MVM Partner作为聚合器提供灵活性服务,管理平衡服务。 5. 数据:安装管理容量155MW,可用容量105MW,最大平衡容量85MW。 6. 挑战:测试运行中遇到电解器#2的断路器故障等问题。 结论: 项目已取得实质性进展,目标是为电网提供可靠的平衡服务,目前正处于调试和优化阶段。CEOÁkos Kriston强调项目无回头路,需积累运营经验并解决后续问题。
"氢储能项目进展如何?" "HGS的Aquamarine项目有哪些亮点?" "Ákos Kriston谈氢能挑战"
客服
商务合作
小程序
服务号
折叠