1、How TSOG Improved Travel,Energy and Future Readiness in RotherhamBy James Drinkall BSc(Hons)FIHEProject EngineerIntroductionTraffic Signals Obsolescence GrantThe Bid The AwardPlanningDesign ChoicesDelivery Lessons learned BenefitsSummary QuestionsThe BidFocus on A631 Key route corridor.Support emerg
2、ing technologies.100%spend on street.Complete within 6 months.Thanks to Marc Roberts and Andy Knowles.The AwardWe were successfully awarded the full 500k from DfT.Plus 96k from SYMCAWe committed to spending all the awarded money on the traffic signals equipment.PlanningUpgrade 24 sites.14 sites alon
3、g A631 corridor.9 funded by TSOG.15 funded by RMBC capital.Early Contractor Involvement.Design Choices-DetectionMOVA as standard.New and emerging technologies.Traficam AI for general traffic detection.AGD650 for cycle detection and bus priority at bus gates.Design Choices-CommunicationsObsolete lega
4、cy equipment.Upgrade to 4G/5G,Wireless and Fibre.High Speed,High CapacityDeliveryChallenging rolling programme.Engaged with Swarco.Placed orders early.Secured delivery lead times.Committed Resources.Morrisons-BramleyWickersley Roundabout Pt1Wickersley Roundabout Pt2West Bawtry Rd Long LaneSummaryPro
5、gramme finished November 2024.On time and on budget.Open to being a test bed.Blank canvas for new technologies/methods of control.Credit AI TimesLessons LearnedConcerns about Technology.Included 6m poles.Drill down more into costs of each sites.Early engagement meant we could deliver what we set out
6、 on budget.Training in using new equipment.Tight deadlines.Traffic Management costs.BenefitsEnergy Savings and Carbon ReductionBenefits4%reduction in journey time.Pedestrians better served.Overall reduction in delay.Less stops starts means