1、rsted Green bond investor letter 2019 January 2020 2 2 Lets create a world that runs entirely on green energy 3 4 Highlights Executive summary 6 Financing green matters 8 Offshore wind 9 Project overview 10 Allocated proceeds Total amounts allocated by bond Bond allocations by project 12 Avoided emi
2、ssions and people powered 13 Green financing governance 14 Project deep-dives Hornsea 1 Changhua 1 much bigger and further from shore than ever seen before”. Covering an area of 407 square kilometres, Hornsea 1 is located 120 km from the Yorkshire coast, the furthest from shore an offshore wind farm
3、 has ever been built. The first turbine was installed in February 2019 and nine months later, in November, all 174 turbines had been successfully installed. The 190-meter-tall turbines, with each individual blade stretching 75 metres in length, takes up to 12 hours of precision working to install. W
4、hen commissioned, each turbine produces enough electricity to be able to individually power a UK home for over one day with a single rotation. “This flagship project demonstrates globally that large- scale renewable electricity generation that competitively replaces fossil fuel generation is not onl
5、y possible, its here already”, said Duncan Clark. He went on to add: “Hornsea 1 represents a significant milestone in the global fight against climate change, paving the way for other large-scale offshore wind projects, and bringing us one step closer to our vision of a world that runs entirely on g
6、reen energy.” The electricity generated by the turbines will pass via undersea cables through one of three massive offshore substations, and the worlds first offshore reactive compensation station, all fully installed, before reaching shore at Horseshoe Point, Lincolnshire. The electricity is then t