1、DWEE Permitting OverviewPower SummitOctober 1,2025Presented by:Reuel Anderson,AdministratorPermitting and EngineeringOctober 1,20251DWEE PermittingPermitting and Engineering ProgramsAir Construction and OperatingIntegrated Waste and RCRANational Pollutant Discharge Elimination System(NPDES)Drinking
2、Water and Wastewater ConstructionConcentrated Animal Feeding Operation(CAFO)-Construction and Operating2Other DWEE Permitting ProgramsDam SafetyCAFO NPDES PermitMineral ExplorationOn-site Wastewater Treatment Operating PermitUnderground Injection ControlSurface Water Permithttps:/dwee.nebraska.gov/P
3、ermitting Process Overview1.Application Submittal2.Administrative and Technical Review Internal3.Document Drafting4.Internal Review Internal5.Compliance Review InternalOctober 1,202536.Supervisor Review Internal7.Courtesy Source Review External8.Public Notice(if applicable)External9.Public Hearing(i
4、f applicable)External10.Final Review and IssuancePermitting Process Overview2.Administrative and Technical Review:October 1,20254What is it?This step involves review of different parts of the application to ensure it accurately portrays the project.Common speedbumps:Not being registered with Secreta
5、ry of State;Responsible Official designation;Fee amount/submittal(if applicable);Not submitting proper documentation(i.e.:calculation sheets,specification sheets,etc.)Permitting Process Overview3.Document Drafting:October 1,20255What is it?This step involves preparing the permit documents(i.e:calcul
6、ation sheet,permit,and fact sheet)based on the application.Common speedbumps:Not submitting proper documentation(i.e.:calculation sheets,specification sheets,etc.)Changing scope of the project(i.e.:adding new things,modifying proposed limitations,etc.);Delays in responding to communication request t